Manufacturing
What is TNA (time and action) in the garment industry?
TNA, short for time and action calendar, is the dated list of every step a garment order must pass, from order confirmation and sample approval to fabric arrival, cutting, sewing, final inspection and ex-factory. It is worked backwards from the buyer's ship date, gives each milestone an owner, and sets planned dates against actual ones so a delay shows early.
A typical TNA for an order leaving the factory on 30 April
Each milestone is a number of days before ex-factory. The lead times below are a common starting point for a repeat style; a new style with lab dips and fit samples needs a longer plan.
| Days before ex-factory | Planned date | |
|---|---|---|
| Order confirmed | 35 | 26 March |
| Pre-production (PP) sample approved | 32 | 29 March |
| Fabric in-house | 25 | 5 April |
| Trims in-house | 23 | 7 April |
| Cutting starts | 20 | 10 April |
| Sewing starts | 17 | 13 April |
| First output off the line | 14 | 16 April |
| Finishing and packing | 6 | 24 April |
| Final inspection | 3 | 27 April |
| Ex-factory | 0 | 30 April |
How a merchandiser builds a TNA
A TNA is built when the order is confirmed and kept up to date until the goods leave. Its value is in the weekly update, not in the first draft.
- Start from the ship date
- Take the buyer's ex-factory or shipment date as fixed, and count every milestone back from it.
- List the milestones
- Include sampling, lab dips and approvals, fabric and trims arrival, cutting, sewing, washing or finishing, inspection and dispatch.
- Set lead times
- Use the real lead time for each step: the mill's fabric delivery time, the trim supplier's, the line's daily output for the order quantity.
- Give every milestone an owner
- One named person for each date: the merchandiser for approvals, the store for fabric, the production manager for sewing.
- Record actual dates
- Enter the actual date as each milestone happens. The gap between planned and actual is the early warning.
Where a TNA usually slips
Most late shipments start with an approval or a material arriving a few days late, long before the line is involved.
Approvals
A PP sample or lab dip approved a week late pushes fabric, cutting and sewing by the same week unless the plan has slack.
Fabric and trims
Fabric from the mill and trims such as zips, labels and buttons are the most common late milestones. Chase them before their date, not after.
Already late on day one
If the order is confirmed with less time than the lead times need, some milestones fall before today. Say so to the buyer before accepting the date.
Colour codes
Many teams mark each milestone red when overdue, amber when due within a few days and green when on track or done.
How Dhaaga keeps a TNA for each order
Dhaaga's Time and Action module builds the TNA from the order's ship date and fills in actual dates from the records the factory already keeps.
Back-scheduled from the ship date
Enter the ex-factory date and the plan is laid out backwards from it, from order confirmation to dispatch.
Late before it starts
Milestones whose planned date is already past on the day the plan is built are listed, so the risk is known before the order is accepted.
Actual dates from documents
Actual dates are taken from records such as the fabric receipt, the first cutting lay, the first output and the dispatch. A date someone typed is never overwritten.
Late milestones across orders
Each milestone shows red when overdue and amber when due within three days, and a list gathers every late milestone across all orders, most late first.
Questions people ask first.
Time and action, often written T&A. The TNA calendar or TNA chart is the schedule of actions and their dates for one order.
The merchandiser handling the order prepares and updates it, with dates agreed with the store, production and quality teams.
A TNA tracks one order from confirmation to shipment, including approvals and materials. A production plan schedules the lines across all orders.
The date the finished goods leave the factory for the buyer or the port. The whole TNA is counted back from it.
The pre-production sample, made in the actual fabric and trims, which the buyer approves before bulk cutting starts.
At least weekly, and daily in the last two weeks before ex-factory. A TNA that is updated only when the buyer asks is usually already wrong.
Put one real day through it.
Not a sandbox with sample data — your own bills, your own items, your own customers. By evening you will know whether this runs your business.