Planning kya karta hai
Order ko line aur din se jodta hai.
Aapke paas teen line hain aur aath order. Production Plan ek plan me kuchh style aur unki qty rakhta hai, us par MRP chalata hai (kaunsa maal kam hai), phir Work Order aur Material Request nikalta hai. Lines, Capacity, Schedule, Calendar aur Variance tab uske aage-peeche ka hisaab dikhate hain.
Line set karna
App me: Production Plan › Lines
- Lines tab kholo aur header ke neeche "Nayi line jodo" dabao — beech screen par dialog khulta hai.
- Line ka naam daalo — wahi jo floor par bola jaata hai, jaise Line 1 ya Cutting Section.
- Capacity / din bharo — ek din me kitne piece nikalte hain.
- Stage chaho to chuno (optional) — nahi chuna to "Koi bhi".
- Status "Chalu" rakho.
- Footer me "Line save karo" dabao.
Banayi hui line badalni ho to us row ka "Badlo" dabao — wahi chaar khaane wala dialog us line ke saath bhar kar khulta hai, sirf title "Line badlo" ho jaata hai. Row ke doosre do button — "Band karo" aur "Hatao" — dialog nahi kholte; "Hatao" pehle poochhta hai.
- Line ka naam
- Floor par jo bola jaata hai wahi. Capacity board aur bundle issue dono me yahi naam dikhega.
- Capacity / din
- Piece per din. Poori Capacity screen isi ek number par tiki hai.
- Stage (optional)
- Ye line kis stage ki hai — cutting, stitching, finishing. Khaali chhodne par "Koi bhi".
Naya plan banana
App me: Production Plan › + Naya Plan
- Plan ka naam daalo — jaise "July Week 2".
- Date dekh lo — aaj ki bhari hoti hai, chaaho to badlo.
- Pending orders me se jo banane hain wo tick karo.
- Order me na ho to neeche manual style × qty ki row jodo.
- "Plan save karo". Plan khulte hi "MRP chalao" dabao.
- Plan ka naam
- Hafte ya batch ka naam. List me isi se dhoondoge.
- Qty (pcs)
- Us style ke kitne piece is plan me hain. Order se li hui line par ye order se hi aati hai.
- Kab tak
- Order se aayi line par uski delivery date. Manual line par ye khaali rehti hai.
Capacity — kaunsi line par kitna kaam pada hai
App me: Production Plan › Capacity
Ye screen har line par dikhati hai: kitne piece pending hain, roz ki capacity kitni hai, aur is hisaab se kitne din me saaf hoga. Pending ek din ki capacity se upar gaya to line "Overloaded".
- Capacity tab kholo.
- Upar ke teen tile dekho — kul pending pcs, active lines, aur kitni line overloaded hain.
- Overloaded line ka "Saaf hone mein" kitne din hai wo dekho, aur uske kuch lot dusri line par daalo (line assign Production me hoti hai).
- Sabse neeche "Unassigned" wali row dekho — wo lot hain jo kisi line par hain hi nahi. Kuch bhi unassigned na ho to ye row aati hi nahi.
Schedule aur calendar
App me: Production Plan › Schedule / Calendar
Schedule due date se ulta gin kar har stage ki window nikalta hai — "kaam kab shuru hona chahiye". Calendar aane wale 2 hafte ya mahine ke lot unki due date par dikhata hai, laal = late.
- Schedule: ek lot chuno (ya haath se due date daalo), har stage ke din bharo — shuru aur khatam ki tareekh khud nikal aati hai.
- Calendar: mahine bhar ki tasveer — kaunsa lot kis din due hai aur kaun late ho chuka hai.
- Dono padhne ke liye hain: yahan lot ko kheench kar khiskaya nahi ja sakta.
Variance — plan aur asli ka farq
App me: Production Plan › Variance
Plan me is style ke 400 piece the, bane 310. Variance yahi farq dikhata hai — ek plan chuno, aur uske har style par Plan, Banaya aur Antar aa jaata hai.
- Variance tab kholo aur upar se plan chuno.
- Jis style ka Antar sabse bada hai wahan ki wajah floor par jaakar poocho — machine, aadmi, ya maal.
- Do din lagatar peeche ho to plan ya line ki capacity badlo, umeed mat karo.
- Meeting ke liye "CSV nikalo" se poori table nikaal lo.
Plan band karna aur cancel
App me: Production Plan › plan kholo
Plan ki chaar haalat hain: Draft, Confirmed, Closed aur Cancelled. Kaam khatam hone par "Plan band karo", aur bilkul na banane par "Plan cancel".
Kab kharidna hai — sirf kya kam hai, itna kaafi nahi
Production → MRP. Yahan do column kaam ke hain: "MR kab tak" aur "Time".
Har item ke saamne ye bhi dikhta hai ki uska request kis din tak nikalna hai, aur uske saath lead time. Ye wahi hisaab hai jo kharidne wala aksar apne dimaag me karta hai.
Upar ek tile hai — "Pehle se late". Us number pe roz nazar daalna kaafi hai.
Plan par: maal kitna aa gaya, aur line sambhal legi ya nahi
Planning → koi plan kholo.
Upar ek bar hai — maal kitna aa gaya. Ye PAISE ke hisaab se hai, line count se nahi.
Har plan line ke saamne "Maal" column hai — book karna hai / book ho gaya / raste me / aa gaya / kam padega. Ye khud PO aur GRN se banta hai, koi type nahi karta.
Neeche "Line pe kitna load hai" — har line ke liye kitne minute ka kaam pada hai aur kitne minute hain. Jis din maang line se zyada ho jaati hai, wo din naam se likha aata hai.
Planning reports
Planning → Reports.
Do report. "Order ke hisaab se" me paanch column hain — order, plan me, floor par, ban gaya, bhej diya.
"Plan ke hisaab se" me sabse upar wo plan aate hain jinki lines par koi work order nahi bana. Aksar wajah ye hoti hai ki release ke waqt us style ka BOM nahi tha.
Har row click hoti hai — order row order par, plan row plan par.
Line board — deewar wala chart, screen par
Planning → Line board.
Har line ek row hai. Plan ki lines chips ki tarah dikhti hain — kheench kar doosri line par daal do, ya neeche "Kisi line par nahi" wale hisse me chhod do.
Har row ke neeche patli din-patti hai. Jo din laal hai, us din line se zyada maang hai. Upar likha aata hai ki wo kaunsa din hai.
Jis line ke ghante set nahi hain uspar "Ghante set nahi" likha aayega — uska load dikhega par laal din nahi banega. Jis style ka SAM nahi naapa, uska naam alag se likha aayega aur wo load me nahi ginega.
Work order reports
Production → WO reports.
Teen view — khule, chal rahe, poore hue. Har work order theek ek me aata hai, isliye teeno ki ginti milkar poori list banti hai.
"Poore hue" me wo jawab milta hai jo yaadon se kabhi nahi milta: humne nau din kahe the, lage chaudah.
List me kisi work order par "Routing nahi" ka nishaan dikhe to uspar job card ban hi nahi sakta. Nishaan par click karo — seedha BOM ki routing par le jaayega.