You make a GRN by checking a delivery against its purchase order, counting what arrived, splitting it into accepted and rejected quantity, and posting only the accepted quantity into stock. The supplier's bill is then checked against the order and the GRN, called the three-way match, before it is passed for payment.

Six steps from the delivery van to the stock register

The same steps work for a carton of medicines, a truck of cement bags or a bale of cloth. Do them on the day the goods arrive, while the driver is still there to sign for a shortage.

6 steps
Pick the purchase order
Open the order the delivery is against. The GRN copies the supplier, items, ordered quantities and agreed rates from it, so nothing is typed twice.
Note the paperwork
Record the supplier's challan or invoice number and date, the vehicle number and the e-way bill number if one came with the goods.
Count and inspect
Count every line and check quality: broken tiles, leaking oil tins, torn cartons, short-length rolls, the wrong size or colour.
Split accepted and rejected
Enter the quantity received, then the quantity rejected with a reason. Accepted quantity is received minus rejected.
Add batch and location
For items with a batch or an expiry date, enter both. Note the godown or rack where the goods are put away.
Post the GRN
Posting adds only the accepted quantity to stock. The purchase order then shows what is still pending from the supplier.

A hardware shop receives 50 boxes of floor tiles

The order was for 50 boxes at ₹600 a box. All 50 arrived, 3 were broken, and the supplier billed for 50.

47 of 50
GRN and bill for an order of floor tiles at ₹600 a box
 QuantityValue
Ordered on the purchase order50 boxes₹30,000
Received at the gate50 boxes₹30,000
Rejected as broken3 boxes₹1,800
Accepted into stock47 boxes₹28,200
Billed by the supplier50 boxes₹30,000
Debit note, or pay less3 boxes₹1,800 plus the GST on it

The three-way match: order, receipt and bill must agree

Before a supplier bill is paid, three documents are laid side by side for each item. Any difference is either explained or recovered.

3 documents
  • Quantity

    Billed quantity should not exceed accepted quantity. In the example, 50 billed against 47 accepted is 3 boxes too many.

  • Rate

    Billed rate should match the order rate. A small tolerance, such as 1 percent, stops rounding from flagging every bill.

  • Tax and total

    Check the GST rate, the HSN code and the supplier's GSTIN on the bill, since input credit depends on them.

  • When they differ

    Hold the payment, raise a debit note for the difference, or accept the bill knowingly with a note of why.

How Dhaaga records a GRN

A GRN is made from the purchase order, and the supplier bill is made from the GRN, so each step reads the one before it.

PO → GRN → bill
  • GRN from the order

    The GRN form opens from a purchase order and can take in more than one order from the same supplier.

  • Accepted and rejected on each line

    Every line holds the quantity received, accepted and rejected, a rejection reason, a batch number and a storage location.

  • Bill only what was accepted

    A supplier bill drafted from GRNs carries the accepted quantity. Billing the rejected quantity is a separate, deliberate choice.

  • Three-way match on the bill

    The bill compares ordered, accepted and billed quantity and rate for each item, within the rate tolerance set in buying settings. A difference has to be acknowledged before the bill is saved.

Questions people ask first.

6

Goods receipt note, sometimes called goods received note. It is the record that goods arrived, how many, and in what condition.

The person who receives the goods: the store keeper, godown in-charge or the shop owner in a small business. The accounts side uses it later to pass the supplier bill.

Yes, for goods bought without an order, such as an urgent cash purchase. There is then no order to check quantity and rate against, so the bill gets only a two-way check.

They stay out of saleable stock and go back to the supplier on a return, with a debit note for their value. If the supplier replaces them, the replacement comes in on a fresh GRN.

No. The delivery challan is the supplier's document that travels with the goods. The GRN is your own record of what you actually received and accepted.

GST law does not prescribe a GRN format. But input tax credit is allowed only on goods actually received, under section 16(2)(b) of the CGST Act, and a GRN is the usual proof of receipt.

The fastest honest test